This shows you the differences between two versions of the page.
Both sides previous revision Previous revision Next revision | Previous revision Next revision Both sides next revision | ||
spaceprojs [2019/01/06 01:22] kathughett |
spaceprojs [2019/05/28 21:05] kathughett |
||
---|---|---|---|
Line 9: | Line 9: | ||
===== Current To Do List ===== | ===== Current To Do List ===== | ||
- | ==== Punch List for January | + | ==== Punch List for May 2019 (June 2) ==== |
- First thing - Vacuum cafe area and meeting room. | - First thing - Vacuum cafe area and meeting room. | ||
- Second thing - Sanitize cafe tables and meeting room tables. These need to be done before the food or any snacks are set up. | - Second thing - Sanitize cafe tables and meeting room tables. These need to be done before the food or any snacks are set up. | ||
- Empty the vacuum cleaners as well as the floor sweeper in the main alley entrance. (It's a dusty maroon color) | - Empty the vacuum cleaners as well as the floor sweeper in the main alley entrance. (It's a dusty maroon color) | ||
- | - Vacuum Cafe area at the end of the day after the feast. | + | - Clean out the Toaster, Toaster Oven, and Microwave |
- | - Red ticket abandoned projects in East Room. | + | - SUPERIMPORTANT: |
- | - We need a hero to suck out the dead mice from 3D printing and under the shelves GA112 & GA113. | + | - More work needed on the compressed air dryer (See Markus or Tom G.) |
- | - Install suspended electrical hookup above craft lab table. | + | - Revamp |
+ | - Move bookcase | ||
+ | - Make smaller bookcases up for grabs for 1 week. | ||
+ | - Replace | ||
+ | - Scrub the sinks in the mud room. | ||
+ | - If the grill is used during SID assign someone to clean it at the end of the day.(See instructions below) | ||
- See if there are enough trash bags in the green supply cabinet by the men's room. If not enough, buy more now. | - See if there are enough trash bags in the green supply cabinet by the men's room. If not enough, buy more now. | ||
- | - Build "Third Wall" in the Impound Lot. (See Kathryn for Instructions) | ||
- | - Disseminate contents of IMPOUND LOT. | ||
- | - Deal with trip hazard by pinball machine (See Markus for details.) | ||
- | - Organize the paint room shelves. Dust off cans. | ||
- | - Install additional security cameras if necessary. (Tony if he feels like it and if we have them) | ||
- | - Mount racks for gas tanks along outside of welding shop wall? | ||
- Inventory storage, find lapsed storage still in use (Ongoing for Facilities Director) | - Inventory storage, find lapsed storage still in use (Ongoing for Facilities Director) | ||
- | - {{: | + | - {{: |
- Check and restock first-aid kits, (and update the page [[miscellaneous: | - Check and restock first-aid kits, (and update the page [[miscellaneous: | ||
- Replace wash sink water filters (and update the page [[miscellaneous: | - Replace wash sink water filters (and update the page [[miscellaneous: | ||
- Replace furnace filters if needed (and update the page [[miscellaneous: | - Replace furnace filters if needed (and update the page [[miscellaneous: | ||
- | - Replace wood shop air filters (ongoing) | + | - Replace wood shop air filters (ongoing) |
- | - Look at electric strikeplate on the front door. Repair and/or order replacement (The BOD has already appropriated funds if this is needed) | + | - Disseminate contents of Impound Lot IF needed. |
- | - Revamp the Cafe area and build a large rolling island with cabinets below for storage(See Kyle). | + | - Vacuum |
- | - Craft Lab: - Organize scrap materials, throw away silly (e.g. tiny and/or unusable) pieces, Organize and evaluate supplies with Make-a-thon in mind. | + | - Red ticket abandoned projects in East Room. |
- | - Clean up Cosplay room. Clear path to server room door. | + | |
- | - Paint wall behind dining table in Lobby area. (Colleen & Kathy need to choose a paint color first) | + | |
- | - **Install additional lights in vault hallway.** (brought in by Matt Melk).(Does anyone still feel that we need to do this?) | + | |
+ | - make sure parking ticket holders are sufficiently stocked | ||
+ | - clean out vacuum cleaner filters | ||
+ | - Finish Milwaukee Tools Cabinet | ||
+ | - Paint wall in Lobby area. (Project on hold) | ||
===== Standing To-Do/ | ===== Standing To-Do/ | ||
Line 51: | Line 54: | ||
- Clean bathrooms | - Clean bathrooms | ||
- Inventory member storage against a printout of the wiki, then crosscheck that with active member list (Board member needed for this) so we can clear off empty spaces. (Ongoing by Kathy H.) | - Inventory member storage against a printout of the wiki, then crosscheck that with active member list (Board member needed for this) so we can clear off empty spaces. (Ongoing by Kathy H.) | ||
+ | |||
+ | ==== Cleaning the Grill ==== | ||
+ | When you've finished using the grill heat it up to burn off the crud. Once the remains are burnt to ash use a grill brush to remove the remaining bits. Turn the grill to medium heat and apply vegetable oil to the grates. Let the grill cool down completely before putting on the fabric cover. | ||
+ | |||
+ | At the end of grilling season view this video for a thorough cleaning of the grill. https:// | ||
==== Website ==== | ==== Website ==== | ||
Line 62: | Line 70: | ||
- Parking sign for Building - electronic (still desired? | - Parking sign for Building - electronic (still desired? | ||
- Finish the exterior south east entrance (vault hall). | - Finish the exterior south east entrance (vault hall). | ||
- | - Paint new brick work outside the building by the welding and paint booth vents. | + | - Paint new brick work outside the building by the welding and paint booth vents. Need to find out from Tom G. what and where. |
- Repair broken bricks & tuckpointing around the outside of the building. | - Repair broken bricks & tuckpointing around the outside of the building. | ||
Line 72: | Line 80: | ||
- Get an ice maker working in one of the refrigerators (kegerator has one) | - Get an ice maker working in one of the refrigerators (kegerator has one) | ||
- Re-stripe the exit aisles - add some diagonal stripes so people know what part is aisle. | - Re-stripe the exit aisles - add some diagonal stripes so people know what part is aisle. | ||
- | - Access control system at Vault entrance - Royce P. | ||
- Paint new brick work inside the vault hall | - Paint new brick work inside the vault hall | ||
- Replace steel floor plates covering holes, or Flatten and weld reinforcements on them so they won't bend if the forklift drives over them - Dan J. | - Replace steel floor plates covering holes, or Flatten and weld reinforcements on them so they won't bend if the forklift drives over them - Dan J. | ||
- | - Fix the louvers on the weld shop fan so they close correctly. - Dan J. | + | |
==== Laser Lab ==== | ==== Laser Lab ==== | ||
Line 85: | Line 92: | ||
===== Completed Projects ===== | ===== Completed Projects ===== | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | -< | ||
- < | - < | ||
- < | - < | ||
Line 166: | Line 190: | ||
< | < | ||
- <del> Exhaust fan and hood for the pottery area - See Tom G. or Brant H.</ | - <del> Exhaust fan and hood for the pottery area - See Tom G. or Brant H.</ | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
+ | - < | ||
[[miscellaneous: | [[miscellaneous: | ||
[[miscellaneous: | [[miscellaneous: |