Status

  • Contacted 11/20/2014
  • Started 03/20/2015
  • Finished –/–/—-
  • Due date mid-June 2015

Timeline

2015/03/20 - First paper mock-up to tweak dimensions/pieces

2015/05/01 - Second mock-up

2015/05/01 - Third mock-up

2015/05/01 - Fourth mock-up

2015/05/01 - Fifth mock-up

2015/07/08 - Assembly

2015/07/09 - Painting

2015/07/10 - Completed

Notes

  • Commission work from a client in California