Norwich Punch-List
These tasks need to be completed before the area can be useable. This is neither a definitive nor final list, and will be constantly updated.
Meeting Room
Carpeting (~5 days); must be done first, can start when we have the carpet glue (est. Wednesday the 16th); requires ~2+ people, but more are encouraged; requires knee pads
General layout (ongoing)
AV meeting equipment (1+ people); (needs basic cable management skills and possibly basic power tools)
Machine Shop
General layout of equipment (ongoing); requires pallet jack and forklift
Bandsaw
Cleaning rust, scraping flat; requires 1+ person/people
Woodshop
General layout of equipment (ongoing); requires pallet jack and forklift
Dust collection system (ongoing); requires scissor lift and basic hand tools
Contact Markus S.
Fixing equipment
Current volunteer for scraping surfaces: Wolfgang; additional volunteers needed
Paint Booth
Needs Volunteer to Coordinate Volunteers
Installation of draft wall (1-3 days)
Need ~3+ volunteers; requires power tools and maybe some muscle
Make/assemble shelves for non-volatile materials (1+ people)
Make/assemble shelves for drying rack (1+ people); approach however you want
Welding Area
General Layout
Find/Assemble tank rack for weld gas
Run electrical (to be done by Makers Village)
Forging Area
Building the forge (contact Alex Grade)
Assemble steel racks
Ceramics
General layout; done by Jeff
Install sink at drain pipe; in progress
Run electrical (to be done by Makers Village)