Paint and Chemical Vault

Rules and Etiquette

  • Use parking passes to tag any projects you are leaving to dry
  • Write notes on dry erase board at your discretion
  • Turn on lights and fans when using the room
  • Contact BrantH. if you have any questions

Equipment

2018 Expansion

  • In March of 2018 the vault next to the Paint Room (Vault #15) was vacant and an opportunity arose to double the size of the current space.
  • A meeting was held on Wednesday, 4/25/18 to discuss proposals and ideas. 14 people attended:
    • Brant H.
    • Tim C.
    • Lyra C.
    • Tony S.
    • Kathy C.
    • Tony W.
    • Tom Grz.
    • Morgan K.W.
    • Jake B.
    • Hiram W.
    • Harvey M.
    • Steve P.
    • Kathy H.
    • Bill C.

Scope

Budget

Schedule/Phasing

  1. 5/21/2018 - Provide proposal to Board for review
  2. 5/22/2018 - Obtain Board approval to proceed
  3. 6/01/2018 - Clear out Vault 15 and remove remaining wood shelf parts from wall (< 1 hr.)
  4. 6/01/2018 - Relocate shelving and paints from Vault 16 to 15 (2-3 hrs.)
  5. 6/01/2018 - Saw cut opening in wall between vaults (30 mins.)
  6. 6/01/2018 - Cut slot for new lintel/steel channels (< 30 mins.)
  7. 6/01/2018 - Install first lintel/steel channel (< 30 mins.)
  8. 6/03/2018 - Cut slot for new steel on other side of wall (< 30 mins.)
  9. 6/03/2018 - Install second lintel/steel channel and secure channels together (< 30 mins.)
  10. 6/03/2018 - Demolish block from new opening (30 mins.)
  11. 6/23/2018 - Clean/deburr inside edges of new opening (30 mins.)
  12. 6/23/2018 - Complete relocation of tables/equipment as needed (1-2 hrs.)
  13. 6/23/2018 - Remove existing filter and framing from sidewall fan in Vault 16 (< 30 mins.)
  14. 6/23/2018 - Build diagonal metal frame filter wall at sidewall fan in Vault 16 (2-3 hrs.)
  15. 6/23/2018 - Install blanking panel(s) or baffles at fan (< 30 mins.)
  16. 6/24/2018 - Cover filter wall with wire mesh and roll filter mesh (< 30 mins.)
  17. Date TBD - Cut new air grille into Vault 15 door (< 30 mins.)
  18. Date TBD - Relocate air hose and regulator out from under wall fan in Vault 16 (1-2 hrs.)