 ====== Paint and Chemical Vault ====== ====== Paint and Chemical Vault ======
  
 +Area Champion
 +  *[[members:johnklein|John Klein]]
 ===== Rules and Etiquette ===== ===== Rules and Etiquette =====
-  * Use parking passes to tag any projects you are leaving to dry +  * Use parking passes to tag projects that are drying. 
-  * Write notes on dry erase board at your discretion +  * Move drying projects to the "clean" side to make space for other members as soon as you are able. 
-  * Turn on lights and fans when using the room +  * Avoid using the paint room late night/early morning when the weather is nice. If the neighbors have their windows open the noise of the vent may be obnoxious. 
-  * Contact BrantH. if you have any questions+  * Turn on the exhaust fan whenever you are using __any__ chemicals that produce vapors or odor. 
 +  * Leave the fan on for a few minutes after you are done with the room to clear out lingering vapors. 
 +  * Stay out of the dirty side of the room if someone else is actively painting, especially if they are using something that requires lung protection. 
 +  * All paint/chemicals are free for any member to use unless otherwise marked.
  
-===== Equipment ===== +===== Training =====
-  * [[Equipment/benchspraybooth|Bench-top Spray Booth]] +
-  * {{:equipment:partwash.jpg?100|}}[[Equipment/PartsWasher|Parts Washer]] +
-  * {{:equipment:exhaustfan02.jpg?100|}}[[Equipment/ExhaustFan2|Paint Room Exhaust Fan]] +
-  * {{:equipment:h95.png?100|}}[[Equipment/H95|H-95 Vacuum Pump/Aspirator]] +
-  * [[Equipment/2016inventory|August 2016 inventory of Paint Room]]+
  
 +Members must be trained to use the HVLP spray gun and the pneumatic paint shaker. Text [[members:johnklein|John]] to schedule training.
 +
 +General use of the paint room does not require training. 
 ===== 2018 Expansion ===== ===== 2018 Expansion =====
-  * In March of 2018 the vault next to the Paint Room (Vault #15) was vacant and an opportunity arose to double the size of the current space.   +  * In March of 2018 the vault next to the Paint Room (Vault #15) was vacant and an opportunity arose to double the size of the current space.  [[areas:paintexpansion|Project details]]
-  * A meeting was held on Wednesday, 4/25/18 to discuss proposals and ideas.  14 people attended:  +
-      * Brant H. +
-      * Tim C. +
-      * Lyra C. +
-      * Tony S. +
-      * Kathy C. +
-      * Tony W. +
-      * Tom Grz. +
-      * Morgan K.W. +
-      * Jake B. +
-      * Hiram W. +
-      * Harvey M. +
-      * Steve P. +
-      * Kathy H. +
-      * Bill C. +
-==== Scope ==== +
-{{:areas:2018paintroomplan.jpg?600|}}\\ +
-{{:areas:paintroom-wallopening-final.pdf |Click here for a PDF}} +
-==== Budget ==== +
-  * Estimated total cost = $373 +
-  * Metal framing (approx. 87 lineal ft.) +
-    * (4) 10 ft. verticals = 40 ft. +
-    * (6) 5.4 ft. kickers = 32.3 ft. +
-    * (2) 6-7 ft. base/top plates = 14 ft. +
-    * Home Depot $3.59/8 ft. length +
-    * https://www.homedepot.com/p/ClarkDietrich-ProSTUD-25-3-5-8-in-x-8-ft-25-Gauge-EQ-Galvanized-Steel-Wall-Framing-Stud-360081015/100319022 +
-    * Total likely $43 w/ tax +
-  * Roll filter media (approx. 60 sq.ft.) +
-    * Grainger $18 w/o S&H +
-    * 20 ft. x 36" MERV: Less Than 5 +
-    * https://www.grainger.com/product/AIR-HANDLER-20-ft-x-36-Filter-Media-Roll-2W186 +
-  * (2) Wide flange steel channels +
-    * Tom working on this  +
-    * Harrison Metals might have something +
-    * MetalsDepot, 8" tall, 2.5" wide  72" long, A-36 Steel Channel, $156 ea. +
- +
- +
- +
-==== Schedule/Phasing ==== +
-  - Date TBD - Provide proposal to Board for review +
-  - Date TBD - Obtain Board approval to proceed +
-  - Date TBD - Clear out Vault 15 and remove remaining wood shelf parts from wall +
-  - Date TBD - Relocate shelving and paints from Vault 16 to 15 +
-  - Date TBD - Cut new air grille into Vault 15 door +
-  - Date TBD - Relocate air hose and regulator out from under wall fan in Vault 16 +
-  - Date TBD - Remove existing filter and framing from sidewall fan in Vault 16 +
-  - Date TBD - Build diagonal metal frame filter wall at sidewall fan in Vault 16  +
-  - Date TBD - Install blanking panel(s) or baffles at fan +
-  - Date TBD - Cover filter wall with wire mesh and roll filter mesh +
-  - Date TBD - Saw cut opening in wall between vaults +
-  - Date TBD - Install temporary jack posts for spancrete ceilings? +
-  - Date TBD - Demolish 1/2 depth portion above opening for new lintel/steel channels +
-  - Date TBD - Install first lintel/steel channel +
-  - Date TBD - Demolish remaining 1/2 depth portion on other side of wall +
-  - Date TBD - Install second lintel/steel channel and secure channels together +
-  - Date TBD - Demolish block from new opening +
-  - Date TBD - Clean/deburr inside edges of new opening +
-  - Date TBD - Complete relocation of tables/equipment as needed +
- +