Entry system
Construction of (noise proof?) walls for woodshop
Heating system installation
Occupancy permit / inspection date
Planners have seen plans
Inspections still needed, arranged by builders
Electrical will be done by us, separate from rest of buildout
Roof maintenance status & dates
roofers starting Thursday, should be done in one week
will taper the roof insulation
Complete tear off, down to the steel
Leveling the floors and ramps for ADA compliance
New restroom to be created
Doors being added, including overhead door now
Tom has a new 30“ vent fan for Room B, southeast door by vaults will become operable window
Projected Move in duration and dates, so members can plan ahead