Meeting called to order by Markus at 7:02PM
Minutes approved by 6 present
New Business
Current Financial Projections
Update from Dan J
COVID-19 Reopening
Update
Voluntary covid suspensions are being extended.
Members need to let us know if they intend to suspend
Milltronics removal
it has been dragging on for too long
plan
he has one week to get a contract to get the machine moved out of the space. if not out by the end of the month, he will be charged $360/month for taking up the floor space
Richard has been notified, no response but the machine has been put on craigslist
UPDATE *
Richard has been paying the rent on the space.
Makers Village (Norwich Building)
Background
Makers Village would like to sign a lease with Milwaukee Makerspace